Power Transmission & Substation
Year 2024 33kV & 220kV
220kV Electrical Substation HT Cable Laying & Heavy-Duty HDG Tray Erection
Location Navi Mumbai, Maharashtra
Scope Mode Turnkey (Material Supply + On-Site Execution)
Execution Time 45 Days
Compliance 100% Passed
Audited Site Deliverables & Achievements
- ✓ Fabricated and erected 1,800 running meters of 600mm Hot Dip Galvanized ladder trays (86 micron coat).
- ✓ Laying and dressing of 33kV XLPE Aluminium Armoured cables in indoor and outdoor trenches.
- ✓ Completed 48 heat-shrink straight joints and termination kits with zero breakdown upon 24-hr soak test.
- ✓ Delivered test certificates (MTC & CPRI/ERDA compliance) prior to line charging.
Project Overview
Anshika Enterprises was awarded the turnkey electrical contract for high-tension cable routing, structural steel tray erection, and cable terminations at a 220kV switchyard expansion project in the Navi Mumbai industrial corridor.
Engineering Challenges
- High Fault Current Requirements: Demanded strict adherence to heavy rung pitch (250mm) on ladder trays to withstand short-circuit electromagnetic repulsion forces.
- Tight Shutdown Windows: Critical interconnects had to be laid and terminated during a scheduled 72-hour utility outage without impacting active transformer bays.
Execution & Scope
- Material Supply: Delivered factory-tested 33kV 3C x 400 sq.mm XLPE cables, hot-dip galvanized ladder trays, and 50x6mm copper earthing strips with Mill Test Certificates.
- Structural Fabrication: Custom fabricated ceiling drops, riser channels, and cantilever supports with anti-vibration clamps.
- Laying & Termination: Employed trained jointing technicians certified for Raychem-standard 33kV heat-shrink outdoor terminations.
- Testing & Commissioning: Megger testing, VLF insulation test, and soil resistivity loop testing witnessed and approved by the chief electrical inspector.